Of the 20 major items experiencing both overstock and stockouts, we narrowed down to five with significant impact, and conducted everything from business issue organization to PoC verification within 10 weeks. This is a proven track record of comparing six cases across three demand scenarios × two inventory policies, and determining the scope to implement next.

itemContents
Target AreaInventory and Production Planning
Support DetailsBusiness Issue Organization, PoC, Analysis & Optimization Design
Period10 weeks (2 weeks for organizing issues, 6 weeks for PoC design/analysis, 2 weeks for organizing implementation policies)
Eligible ItemsOf the 20 major items, 5 have the highest impact
Number of Verification Cases3 demand scenarios × 2 inventory policies = 6 cases
deliverableIssue summary report, PoC code, implementation policy document

Challenges

At 20 major items, both overstock and shortages occurred simultaneously, making it difficult to see which items or processes needed improvement. Analyzing all items at once would take too much time and cost, so it was necessary to first focus on the scope of impact for verification.

Therefore, after organizing business issues and data status, we narrowed down to five items with significant impact and conducted a PoC comparing the combination of demand fluctuations and inventory policies.

How to proceed

Organizing business issues (weeks 1–2)

We identified factors that influenced decision-making, such as inventory, delivery dates, production capacity, and order units, and selected five items with significant impact from 20 options.

PoC Design and Analysis (Weeks 3–8)

For five items, six cases combining three demand scenarios (flat, increase, decrease) and two inventory policies (current operation and review proposals) were compared using demand forecasting and inventory simulation.

Organizing implementation policies (weeks 9–10)

From the comparison results of six cases, we narrowed down the combinations expected to be effective and organized the screens and reports necessary for business operations.

Results

Through comparing five items and six cases, we clarified which items had significant room for improvement and which data items needed to be developed first.

Based on the PoC results, we were able to organize our plan to move toward business reports and estimation tools in the next phase, while also looking ahead to expanding to the remaining 15 items.