All articles →

100 Exercises / Mathematical modeling / Mathematical Modeling 100 Exercises

Using Probability to Evaluate Demand Fluctuations and Equipment Failures

Model demand and equipment failures with probability distributions. Compare stockout risk, expected loss, and CVaR over a common horizon in Python.

Modeling Uncertainty and Risk for Critical Replacement Parts: No.061–No.070

Using fictional industrial replacement parts and heat treatment equipment, we model demand, lead time, yield, and failure time as random variables. We use expected values and standard deviations to describe variation, then calculate prediction intervals, stockout and failure probabilities, and expected losses. These measures help us compare inventory levels and maintenance intervals.

About this material These notebooks were adapted from corporate training delivered by Surikobo or its representative, Hiroshi Wayama, and published with the participating companies’ permission. All data is fictional and does not describe actual companies or factories.

Introduction: Practical Challenges in Manufacturing Covered in This Article

For replacement parts manufacturers, shortages due to surging demand and sudden failures of heat treatment equipment are affecting delivery times. Planning based solely on average demand and mean interval of failure may be efficient under normal conditions, but losses when fluctuations overlap cannot be accounted for.

We use 365 days of demand for three products and a fictional equipment-lifetime model to compare average outcomes with losses in adverse cases.

Common situations on site

  • Inventory is determined solely by average demand, without monitoring demand variation.
  • Treat options with the same expected profit as equal and do not compare the size of the loss.
  • Mechanically applying the same normal distribution to quantity, delivery time, and yield
  • Presenting sales forecasts as a single numerical value and not submitting forecast ranges to management meetings
  • Failure probability and loss during failure are managed separately.
  • Only the option with the highest expected value is selected, without checking tolerance for the worst-case scenario.

Why is this issue so difficult to judge?

Uncertainty refers to “values not being fixed,” while risk is “uncertain results leading to operational losses.” It is necessary to compare failures with low probability but significant impact against frequent but minor demand fluctuations using the same criteria.

We examine distributions, upper quantiles, loss probabilities, expected losses, and average losses in the worst cases.

Exercises in this article

No.Themejudgment
061random variableHow to express demand, delivery dates, and yield
062expected valueHow to compare average results
063Variance and Standard DeviationHow to measure variation
064distribution selectionWhat kind of distribution should match the workload?
065Demand distributionHow to express lead time demand
066Sales forecast rangeHow to show upper and lower sales limits
067Stockout ProbabilityWhat is the risk of stockouts per inventory level?
068failure probabilityWhat is the probability of failure during the maintenance interval?
069expected lossHow to integrate probability and impact
070Decision-makingHow to balance expected outcomes against downside risk

Preparing the Python environment

Run the cells from top to bottom in Jupyter Notebook. [IN: n] marks an input and [OUT: n] its corresponding output. Environment details show the original execution example; version and OS strings will differ on your machine.

No external data is used. Fix random number seeds and simulate them using NumPy, pandas, SciPy, and matplotlib.

Show environment setup
[IN: 1]
%matplotlib inline
%config InlineBackend.figure_format = 'svg'

import platform, sys
import matplotlib, matplotlib.pyplot as plt
from matplotlib import font_manager
import numpy as np, pandas as pd, scipy
from scipy import stats
from IPython.display import display

SEED = 42
rng = np.random.default_rng(SEED)
fonts = {f.name for f in font_manager.fontManager.ttflist}
plot_font = next(
    (f for f in ["Hiragino Sans", "Yu Gothic", "Noto Sans CJK JP"] if f in fonts),
    "sans-serif",
)
plt.rcParams["font.family"] = plot_font
plt.rcParams["axes.unicode_minus"] = False
print(
    f"Python {sys.version.split()[0]} / NumPy {np.__version__} / pandas {pd.__version__} / SciPy {scipy.__version__}"
)
print(
    f"matplotlib {matplotlib.__version__} / font {plot_font} / seed {SEED} / {platform.platform()}"
)

# Show full text in table cells instead of truncating long descriptions.
pd.set_option("display.max_colwidth", None)
[OUT: 1]
Python 3.13.1 / NumPy 2.5.1 / pandas 3.0.3 / SciPy 1.18.0
matplotlib 3.11.0 / font Hiragino Sans / seed 42 / macOS-26.3-arm64-arm-64bit-Mach-O

Fictional data

It generates the 365-day demand for products A, B, and C from a negative binomial distribution. Average demand and variance vary by product, and multipliers for days of the week and season are added. The equipment lifespan is based on a Weibull distribution with a shape parameter of 2.2 and a scale of 420 days.

Show fictional-data setup
[IN: 2]
# These data-generation settings are teaching assumptions, not estimates from a real factory.
dates = pd.date_range("2025-01-01", periods=365, freq="D")
specs = pd.DataFrame(
    {
        "product": ["A", "B", "C"],
        "mean_demand": [95, 58, 28],
        "dispersion": [18, 10, 5],
        "price": [5200, 8400, 14500],
        "unit_margin": [1800, 3100, 5600],
        "shortage_loss": [3500, 6000, 12000],
        "lead_days": [5, 8, 12],
    }
)
rows = []
for i, date in enumerate(dates):
    factor = (0.48 if date.day_of_week >= 5 else 1.0) * (
        1 + 0.14 * np.sin(2 * np.pi * (i - 50) / 365)
    )
    for s in specs.itertuples(index=False):
        mu = max(1, s.mean_demand * factor)
        k = s.dispersion
        p = k / (k + mu)
        rows.append(
            {
                "date": date,
                "product": s.product,
                "demand": rng.negative_binomial(k, p),
                "expected": mu,
            }
        )
demand = pd.DataFrame(rows).merge(specs, on="product")
print(f"Demand records: {len(demand):,} rows (365 days × 3 products)")
display(demand.head(9).style.format({"expected": "{:.1f}", "price": "¥{:,.0f}"}))
[OUT: 2]
Demand records: 1,095 rows (365 days × 3 products)
  date product demand expected mean_demand dispersion price unit_margin shortage_loss lead_days
0 2025-01-01 00:00:00 A 101 84.9 95 18 ¥5,200 1800 3500 5
1 2025-01-01 00:00:00 B 18 51.8 58 10 ¥8,400 3100 6000 8
2 2025-01-01 00:00:00 C 37 25.0 28 5 ¥14,500 5600 12000 12
3 2025-01-02 00:00:00 A 95 85.1 95 18 ¥5,200 1800 3500 5
4 2025-01-02 00:00:00 B 72 51.9 58 10 ¥8,400 3100 6000 8
5 2025-01-02 00:00:00 C 45 25.1 28 5 ¥14,500 5600 12000 12
6 2025-01-03 00:00:00 A 83 85.2 95 18 ¥5,200 1800 3500 5
7 2025-01-03 00:00:00 B 88 52.0 58 10 ¥8,400 3100 6000 8
8 2025-01-03 00:00:00 C 23 25.1 28 5 ¥14,500 5600 12000 12
[IN: 3]
summary = demand.groupby("product", as_index=False).agg(
    average_need=("demand", "mean"),
    standard_deviation=("demand", "std"),
    smallest=("demand", "min"),
    largest=("demand", "max"),
)
display(
    summary.style.format({"average_need": "{:.1f}", "standard_deviation": "{:.1f}"})
)
fig, axes = plt.subplots(1, 2, figsize=(11, 4.2))
for p, g in demand.groupby("product"):
    axes[0].plot(g["date"], g["demand"].rolling(14).mean(), label=p)
axes[0].set_title("14-day moving average of demand by product")
axes[0].set_xlabel("Date")
axes[0].set_ylabel("Demand (units/day)")
axes[0].grid(True, alpha=0.3)
axes[0].legend()
axes[1].boxplot(
    [g["demand"] for _, g in demand.groupby("product")], tick_labels=["A", "B", "C"]
)
axes[1].set_title("Daily Demand Distribution by Product")
axes[1].set_xlabel("Products")
axes[1].set_ylabel("Demand (units/day)")
axes[1].grid(True, axis="y", alpha=0.3)
plt.tight_layout()
plt.show()
[OUT: 3]
  product average_need standard_deviation smallest largest
0 A 82.4 32.5 25 184
1 B 48.9 23.5 10 153
2 C 23.7 13.9 1 77

svg


No.061: Expressing Uncertainty as a Random Variable

Practical context

Expressing demand, lead time, yield, and lifespan as random variables rather than fixed values allows you to handle multiple outcomes and likelihood of occurrence.

Modeling approach

X:Ω→RX:\Omega\to\mathbb{R} is used as a random variable, and the demand DD, delivery LL, and yield YY are represented as distributions. First define each variable’s unit and allowable range.

Check with Python

[IN: 4]
samples = pd.DataFrame(
    {
        "daily demand": rng.negative_binomial(12, 12 / (12 + 80), 10000),
        "lead time": np.maximum(1, rng.normal(8, 1.5, 10000)),
        "yield rate": rng.beta(98, 2, 10000),
    }
)
display(samples.describe(percentiles=[0.05, 0.5, 0.95]).T.style.format("{:.2f}"))
fig, axes = plt.subplots(1, 3, figsize=(12, 3.7))
for ax, col, color in zip(axes, samples.columns, ["#2c7fb8", "#756bb1", "#2ca25f"]):
    ax.hist(samples[col], bins=25, color=color, edgecolor="white")
    ax.set_title(col + "Probability distribution")
    ax.set_xlabel(col)
    ax.set_ylabel("Frequency")
    ax.grid(True, axis="y", alpha=0.3)
plt.tight_layout()
plt.show()
[OUT: 4]
  count mean std min 5% 50% 95% max
daily demand 10000.00 80.02 24.70 13.00 43.00 77.00 124.00 224.00
lead time 10000.00 7.98 1.49 2.14 5.53 7.98 10.48 14.28
yield rate 10000.00 0.98 0.01 0.88 0.95 0.98 1.00 1.00

svg

Interpreting the results

Demand is a non-negative integer, delivery time is a positive continuous value, and yield is 0–1. Choosing a distribution that fits the workload range is the premise for realistic simulation.


No.062: Expressing Average Results Using Expected Values

Practical context

You can compare the average profit for each production volume candidate. However, you cannot determine the range of losses based solely on expected values.

Modeling approach

For a discrete random variable, E[X]=∑xxP(X=x)E[X]=\sum_x xP(X=x). The Monte Carlo calculation estimates profit as margin on fulfilled demand minus unsold-stock costs and shortage losses.

Check with Python

[IN: 5]
d_sim = rng.choice(demand.query("product=='A'")["demand"], size=30000, replace=True)
plans = []
for q in [60, 80, 100, 120, 140]:
    sold = np.minimum(q, d_sim)
    leftover = np.maximum(q - d_sim, 0)
    shortage = np.maximum(d_sim - q, 0)
    profit = sold * 1800 - leftover * 250 - shortage * 3500
    plans.append(
        {
            "Production volume": q,
            "expected benefit": profit.mean(),
            "probability of loss": (profit < 0).mean(),
            "5%point": np.quantile(profit, 0.05),
        }
    )
ev = pd.DataFrame(plans)
display(
    ev.style.format(
        {
            "expected benefit": "¥{:,.0f}",
            "probability of loss": "{:.1%}",
            "5%point": "¥{:,.0f}",
        }
    )
)
fig, ax = plt.subplots()
ax.plot(ev["Production volume"], ev["expected benefit"], marker="o")
ax.set_title("Production volume and expected profit")
ax.set_xlabel("Production quantity (units/day)")
ax.set_ylabel("Expected profit (JPY/day)")
ax.grid(True, alpha=0.3)
plt.tight_layout()
plt.show()
[OUT: 5]
  Production volume expected benefit probability of loss 5%point
0 60 ¥4,188 39.9% ¥-154,500
1 80 ¥67,665 12.0% ¥-48,500
2 100 ¥108,383 2.3% ¥32,400
3 120 ¥126,173 0.3% ¥35,600
4 140 ¥129,515 0.0% ¥32,650

svg

Interpreting the results

The plan with the highest expected profit is generally advantageous, but also check the 5th percentile and loss probability. Your choice depends on your financial capacity and the importance of your customers.


No.063: Expressing Variance with Variance and Standard Deviation

Practical context

Even if average demand is the same, products with larger standard deviations require safety stock and capacity margins.

Modeling approach

Var(X)=E[(X−μ)2]\mathrm{Var}(X)=E[(X-\mu)^2],σ=Var(X)\sigma=\sqrt{\mathrm{Var}(X)}. Scale is adjusted with a coefficient of variation CV=σ/μCV=\sigma/\mu.

Check with Python

[IN: 6]
variability = (
    demand.groupby("product")["demand"].agg(["mean", "var", "std"]).reset_index()
)
variability["CV"] = variability["std"] / variability["mean"]
display(
    variability.style.format(
        {"mean": "{:.1f}", "var": "{:.1f}", "std": "{:.1f}", "CV": "{:.2f}"}
    )
)
fig, ax = plt.subplots()
ax.bar(variability["product"], variability["CV"], color="#fdae6b")
ax.set_title("Demand coefficient of variation by product")
ax.set_xlabel("Products")
ax.set_ylabel("coefficient of variation CV")
ax.grid(True, axis="y", alpha=0.3)
plt.tight_layout()
plt.show()
[OUT: 6]
  product mean var std CV
0 A 82.4 1057.0 32.5 0.39
1 B 48.9 552.5 23.5 0.48
2 C 23.7 192.7 13.9 0.59

svg

Interpreting the results

Standard deviation is in units of the original quantity, variance is the square of the quantity, and CV is dimensionless. CV is useful for comparing different demand scales.


No.064: Selecting a Probability Distribution That Fits Business Data

Practical context

The range and generation process differ depending on the quantity, duration, ratio, and lifespan. Incorrect selection of distribution leads to negative demand and yields exceeding 100%.

Modeling approach

For case count, candidates are Poisson and negative binomial; for positive time, gamma and log-normal; for ratio, beta; and for lifespan, Weibull. Choose based on mean and variance, histogram, and business knowledge.

Check with Python

[IN: 7]
dist_check = demand.groupby("product")["demand"].agg(["mean", "var"]).reset_index()
dist_check["mean ratio of variance"] = dist_check["var"] / dist_check["mean"]
dist_check["Candidate"] = np.where(
    dist_check["mean ratio of variance"] > 1.3,
    "Negative binomial distribution",
    "Poisson distribution",
)
display(
    dist_check.style.format(
        {"mean": "{:.1f}", "var": "{:.1f}", "mean ratio of variance": "{:.2f}"}
    )
)
fig, ax = plt.subplots()
ax.bar(dist_check["product"], dist_check["mean ratio of variance"], color="#9ecae1")
ax.axhline(1, color="black", linestyle="--", label="Poisson Guidelines")
ax.set_title("Demand variance-to-mean ratio")
ax.set_xlabel("Products")
ax.set_ylabel("Variance / mean")
ax.grid(True, axis="y", alpha=0.3)
ax.legend()
plt.tight_layout()
plt.show()
[OUT: 7]
  product mean var mean ratio of variance Candidate
0 A 82.4 1057.0 12.84 Negative binomial distribution
1 B 48.9 552.5 11.30 Negative binomial distribution
2 C 23.7 192.7 8.13 Negative binomial distribution

svg

Interpreting the results

The pooled demand variance exceeds its mean. However, varying means across weekdays and seasons can also increase this ratio. The threshold of 1.3 in the code is a teaching heuristic. Compare observations under similar weekday and seasonal conditions before choosing a distribution.


No.065: Expressing Demand as a Probability Distribution

Practical context

By creating a distribution of lead time demand, you can determine order points based on quantiles rather than averages.

Modeling approach

Simulate lead-time demand DL=∑t=1LDtD_L=\sum_{t=1}^L D_t by resampling historical daily demand, then calculate its mean, 95th percentile, and 99th percentile.

Check with Python

[IN: 8]
a_hist = demand.query("product=='A'")["demand"].to_numpy()
lead = 5
lead_demand = rng.choice(a_hist, size=(30000, lead), replace=True).sum(axis=1)
lead_kpi = pd.DataFrame(
    {
        "average": [lead_demand.mean()],
        "standard_deviation": [lead_demand.std()],
        "95%point": [np.quantile(lead_demand, 0.95)],
        "99%point": [np.quantile(lead_demand, 0.99)],
    }
)
display(lead_kpi.style.format("{:.0f} units"))
fig, ax = plt.subplots()
ax.hist(lead_demand, bins=35, color="#2c7fb8", edgecolor="white")
ax.axvline(
    np.quantile(lead_demand, 0.95), color="#de2d26", linestyle="--", label="95%point"
)
ax.set_title("Product A: five-day demand distribution")
ax.set_xlabel("Five-day demand (units)")
ax.set_ylabel("Frequency")
ax.grid(True, axis="y", alpha=0.3)
ax.legend()
plt.tight_layout()
plt.show()
[OUT: 8]
  average standard_deviation 95%point 99%point
0 411 units 72 units 532 units 583 units

svg

Interpreting the results

Stock equal to mean demand does not necessarily imply a 50% stockout probability; that interpretation applies near the median. Independent resampling from all observed days discards weekday order, seasonality, and serial dependence. Use the quantile corresponding to the target stockout probability as a candidate reorder point.


No.066: Modeling Sales Forecast Ranges

Practical context

Prediction ranges that include uncertainty in demand, price, and yield help assess cash and capacity requirements.

Modeling approach

Use Monte Carlo simulation of monthly sales R=Pmin⁡(D,QY)R=P\min(D,QY) to estimate the median and 80% and 95% prediction intervals.

Check with Python

[IN: 9]
n = 40000
monthly_demand = rng.choice(a_hist, size=(n, 30), replace=True).sum(axis=1)
price = rng.normal(5200, 120, n)
yield_rate = rng.beta(98, 2, n)
capacity = 3000
revenue = price * np.minimum(monthly_demand, capacity * yield_rate)
qs = np.quantile(revenue, [0.025, 0.1, 0.5, 0.9, 0.975])
interval = pd.DataFrame(
    {"indicator": ["2.5%", "10%", "median", "90%", "97.5%"], "Monthly Sales": qs}
)
display(interval.style.format({"Monthly Sales": "¥{:,.0f}"}))
fig, ax = plt.subplots()
ax.hist(revenue / 1e6, bins=35, color="#74c476", edgecolor="white")
ax.axvspan(
    qs[0] / 1e6, qs[-1] / 1e6, color="#fdae6b", alpha=0.25, label="95%Predicted Section"
)
ax.set_title("Predicted distribution of monthly sales")
ax.set_xlabel("Monthly Sales (million yen)")
ax.set_ylabel("Frequency")
ax.grid(True, axis="y", alpha=0.3)
ax.legend()
plt.tight_layout()
plt.show()
print(f"95% prediction interval: ¥{qs[0]:,.0f}–¥{qs[-1]:,.0f}")
[OUT: 9]
  indicator Monthly Sales
0 2.5% ¥10,969,947
1 10% ¥11,602,134
2 median ¥12,838,050
3 90% ¥14,095,645
4 97.5% ¥14,773,267

svg

95% prediction interval: ¥10,969,947–¥14,773,267

Interpreting the results

The forecast range includes not only demand but also uncertainties in price and yield. Use the lower limit for cash flow and the upper limit for capacity planning.


No.067: Expressing Out-of-Stock Risk in Probabilistic Terms

Practical context

By showing the probability of out-of-stock during lead time at each inventory level, you can explain the trade-off between inventory and service.

Modeling approach

P(stockout)=P(DL>I)P(\mathrm{stockout})=P(D_L>I) is estimated through simulation.

Check with Python

[IN: 10]
stock_levels = np.arange(300, 801, 50)
risk = pd.DataFrame(
    {
        "Inventory": stock_levels,
        "Stockout Probability": [np.mean(lead_demand > s) for s in stock_levels],
    }
)
display(risk.style.format({"Stockout Probability": "{:.1%}"}))
fig, ax = plt.subplots()
ax.plot(
    risk["Inventory"], risk["Stockout Probability"] * 100, marker="o", color="#de2d26"
)
ax.axhline(5, color="black", linestyle="--", label="5%Objective")
ax.set_title("Product A: stock and five-day stockout probability")
ax.set_xlabel("Available Stock (units)")
ax.set_ylabel("Stockout probability (%)")
ax.grid(True, alpha=0.3)
ax.legend()
plt.tight_layout()
plt.show()
target_stock = risk.loc[risk["Stockout Probability"] <= 0.05, "Inventory"].min()
print(
    f"Smallest tested stock level with stockout probability at most 5%: {target_stock:.0f} units"
)
[OUT: 10]
  Inventory Stockout Probability
0 300 93.9%
1 350 79.6%
2 400 55.2%
3 450 29.4%
4 500 11.4%
5 550 2.9%
6 600 0.6%
7 650 0.1%
8 700 0.0%
9 750 0.0%
10 800 0.0%

svg

Smallest tested stock level with stockout probability at most 5%: 550 units

Interpreting the results

Increasing inventory lowers stockout probability. The improvement from one additional unit depends on the demand distribution and current stock level; it does not necessarily diminish throughout the range. Choose inventory using both the target stockout probability and holding cost.


No.068: Expressing Failure Risk in Probabilities

Practical context

Expressing equipment lifespan as a probability distribution allows for quantifying the probability of failure before the next maintenance.

Modeling approach

For lifetime measured from new, the Weibull failure probability is F(t)=1−exp⁡[−(t/η)β]F(t)=1-\exp[-(t/\eta)^\beta]. When β>1\beta>1, the hazard rate increases with age. The following comparison assumes maintenance restores the equipment to an as-new condition. For equipment already aged aa, failure probability over the next tt days is [F(a+t)−F(a)]/[1−F(a)][F(a+t)-F(a)]/[1-F(a)].

Check with Python

[IN: 11]
beta, eta = 2.2, 420
days = np.arange(30, 601, 30)
failure_prob = 1 - np.exp(-((days / eta) ** beta))
failure = pd.DataFrame(
    {
        "maintenance interval_days": days,
        "Probability of failure within the period": failure_prob,
    }
)
display(
    failure.iloc[::2].style.format(
        {"Probability of failure within the period": "{:.1%}"}
    )
)
fig, ax = plt.subplots()
ax.plot(days, failure_prob * 100, marker="o", color="#756bb1")
ax.axhline(10, color="black", linestyle="--", label="10%guideline")
ax.set_title("Maintenance intervals and failure probability within the period")
ax.set_xlabel("Maintenance interval (days)")
ax.set_ylabel("Failure probability (%)")
ax.grid(True, alpha=0.3)
ax.legend()
plt.tight_layout()
plt.show()
limit = failure.loc[
    failure["Probability of failure within the period"] <= 0.10,
    "maintenance interval_days",
].max()
print(f"Longest tested interval with failure probability at most 10%: {limit} days")
[OUT: 11]
  maintenance interval_days Probability of failure within the period
0 30 0.3%
2 90 3.3%
4 150 9.9%
6 210 19.6%
8 270 31.5%
10 330 44.5%
12 390 57.2%
14 450 68.8%
16 510 78.4%
18 570 85.9%

svg

Longest tested interval with failure probability at most 10%: 150 days

Interpreting the results

The longer the maintenance interval, the higher the probability of failure. Update the parameters by equipment group using observed failures and replacement histories, and compare them with preventive replacement costs.


No.069: Using Expected Loss to Assess Risk

Practical context

By multiplying the probability of occurrence by the impact amount, different types of risks can be prioritized on a common monetary scale.

Modeling approach

EL=∑jpjLjEL=\sum_jp_jL_j. For rare, severe events, also examine maximum losses and business-continuity requirements.

Check with Python

[IN: 12]
risks = pd.DataFrame(
    {
        "Risks": [
            "PartsAmissing_item",
            "Sudden equipment failure",
            "Quality leakage",
            "emergency transport",
        ],
        "Probability of occurrence": [0.08, 0.12, 0.015, 0.20],
        "Impact amount": [3_500_000, 18_000_000, 45_000_000, 1_200_000],
    }
)
risks["expected loss"] = risks["Probability of occurrence"] * risks["Impact amount"]
risks = risks.sort_values("expected loss", ascending=False)
display(
    risks.style.format(
        {
            "Probability of occurrence": "{:.1%}",
            "Impact amount": "¥{:,.0f}",
            "expected loss": "¥{:,.0f}",
        }
    )
)
fig, ax = plt.subplots()
ax.barh(risks["Risks"][::-1], risks["expected loss"][::-1] / 1e6, color="#fdae6b")
ax.set_title("Expected Loss by Manufacturing Risk")
ax.set_xlabel("Expected loss (million JPY / evaluation period)")
ax.set_ylabel("Risk Events")
ax.grid(True, axis="x", alpha=0.3)
plt.tight_layout()
plt.show()
[OUT: 12]
  Risks Probability of occurrence Impact amount expected loss
1 Sudden equipment failure 12.0% ¥18,000,000 ¥2,160,000
2 Quality leakage 1.5% ¥45,000,000 ¥675,000
0 PartsAmissing_item 8.0% ¥3,500,000 ¥280,000
3 emergency transport 20.0% ¥1,200,000 ¥240,000

svg

Interpreting the results

You can compare high-probability/medium losses and low-probability/massive losses in the same table. Unacceptable risks such as defective products reaching customers are treated as constraints regardless of expected loss ranking.


No.070: Organizing Decisions Considering Uncertainty

Practical context

The policy with the lowest expected cost may differ from the one with the smallest losses in adverse cases. Compare both average losses and tail risk.

Modeling approach

Use the same 360-day horizon for all policies. Sum stockout losses over five-day demand cycles, failure losses over maintenance cycles, and policy costs for 360 days. This simplified model replenishes stock to its target at each demand-cycle start and restores equipment to as-new condition at each maintenance-cycle start. Each maintenance cycle has at most one failure, and failures do not alter demand. Compare mean loss, the 95th percentile, and the mean of the worst 5% of trials (CVaR95).

Check with Python

[IN: 13]
decisions = []
n = 30000
horizon_days = 360
cycle_days = 5
# Shared demand draws make policies comparable over the same 360-day horizon.
cycle_demand = rng.choice(
    a_hist, size=(n, horizon_days // cycle_days, cycle_days), replace=True
).sum(axis=2)
failure_uniforms = rng.random((n, 3))

for name, stock, interval, annual_cost in [
    ("Low cost", 450, 360, 1_200_000),
    ("Balance", 550, 240, 2_100_000),
    ("High reliability", 650, 150, 3_400_000),
]:
    shortage = np.maximum(cycle_demand - stock, 0).sum(axis=1) * 3500
    # Each maintenance cycle starts as new and allows at most one failure.
    full_cycles, remainder = divmod(horizon_days, interval)
    durations = [interval] * full_cycles + ([remainder] if remainder else [])
    failure_probabilities = 1 - np.exp(-((np.array(durations) / eta) ** beta))
    failure_count = (failure_uniforms[:, : len(durations)] < failure_probabilities).sum(
        axis=1
    )
    failure_loss = failure_count * 18_000_000
    total = annual_cost + shortage + failure_loss
    q95 = np.quantile(total, 0.95)
    # Average exactly the worst 5%, including only the required number of ties.
    tail_count = n // 20
    cvar = np.sort(total)[-tail_count:].mean()
    decisions.append(
        {
            "policy": name,
            "Expected Total Loss": total.mean(),
            "95%point": q95,
            "CVaR95": cvar,
            "P(loss > JPY 5 million)": np.mean(total > 5_000_000),
        }
    )
decision = pd.DataFrame(decisions)
display(
    decision.style.format(
        {
            "Expected Total Loss": "¥{:,.0f}",
            "95%point": "¥{:,.0f}",
            "CVaR95": "¥{:,.0f}",
            "P(loss > JPY 5 million)": "{:.1%}",
        }
    )
)
fig, ax = plt.subplots()
x = np.arange(3)
ax.bar(
    x - 0.18, decision["Expected Total Loss"] / 1e6, 0.36, label="Expected Total Loss"
)
ax.bar(x + 0.18, decision["CVaR95"] / 1e6, 0.36, label="CVaR95")
ax.set_xticks(x, decision["policy"])
ax.set_title("Average Loss and Tail Risk by Policy")
ax.set_xlabel("decision-making policy")
ax.set_ylabel("Loss (million yen / 360 days)")
ax.grid(True, axis="y", alpha=0.3)
ax.legend()
plt.tight_layout()
plt.show()
best = decision.loc[decision["Expected Total Loss"].idxmin()]
print(
    f"Minimum expected total loss: {best['policy']} / ¥{best['Expected Total Loss']:,.0f}"
)
[OUT: 13]
  policy Expected Total Loss 95%point CVaR95 P(loss > JPY 5 million)
0 Low cost ¥13,944,103 ¥23,963,500 ¥24,472,276 69.6%
1 Balance ¥7,993,414 ¥20,572,500 ¥25,921,246 30.0%
2 High reliability ¥7,200,311 ¥21,400,000 ¥25,470,929 20.0%

svg

Minimum expected total loss: High reliability / ¥7,200,311

Interpreting the results

Under these assumptions, the high-reliability policy minimizes mean loss, while the low-cost policy minimizes CVaR95. The model allows at most one failure over 360 days for the low-cost policy, but one per maintenance cycle for the others; this assumption affects the ranking. Review post-failure recovery, acceptable losses, and customer and safety requirements before selecting a policy.


Practical lessons

  1. Expressing uncertain workloads as random variables that fit the value range
  2. Include the expected value and standard deviation and quantile points together
  3. The distribution is chosen from the process of generating the business and the average variance.
  4. Forecasts are shown not as individual points, but as intervals
  5. Connecting stockouts and breakdowns to inventory and maintenance using probabilities
  6. Integrate probability and impact into expected loss
  7. Use CVaR and constraints for low-frequency massive losses
  8. Policies are evaluated based on both average outcomes and deterioration tolerance

Preparing for practical use

1. Determine the Scope and Unit of Uncertainty

Define demand, delivery time, yield, failure, and price without confusing them.

2. Keeping a history of out-of-stock, malfunctions, and maintenance

It records not only normal data but also right-censored lifetimes, delays, lost orders, and impact amounts.

3. Testing the distribution assumption

We check and regularly update histograms, quantiles, fit levels, and process knowledge.

4. Agree on loss parameters

Gross profit, stoppages, emergency transportation, customer impact, safety, and legal matters are organized by the relevant departments.

5. Conduct backtesting and stress tests

Stress-test policies under demand surges, supply stoppages, and repeated failures.

6. Set decision-making rules

Decide which of the approval criteria should be expected value, service level, maximum allowable loss, or CVaR.

Conclusion

No.061–070 represent demand, sales, stockouts, and failures as probability distributions, and link expected value, standard deviation, forecast interval, expected loss, and CVaR to decision-making. Rather than eliminating uncertainty, it is important to visualize the range of results and the size of losses, and compare inventory and maintenance options.

Support for businesses

At Surikobo, we support probabilistic models for demand, delivery time, and yield, stockout/failure risks, predictive intervals, Monte Carlo simulations, and inventory and maintenance decisions that consider risks.

📩 Contact Us: www.surikobo.co.jp/contact Please feel free to consult us first.